The key to success is to keep the cutover time as short as possible. Plan for all stages of the clinical system migration. Include any workarounds to help ease the migration between the two systems.
Planning for cutover
Cutover is the time between the final data production (FDP) from the current system and go live on the new system.
Practices need to decide on a plan to reduce the impact as much as possible. The cutover plan should take into account how the cutover period will impact things such as :
- day to day processes, for example appointments
- how repeat prescriptions will be affected
- test requests that have been issued just prior to the cutover
- workflow requests
- referrals that are in progress at the time of the cutover
- the gap between the final data production from the current GP clinical system and the new GP clinical system being available
-
how will patient facing services be impacted, for example will the NHS App be available for patients
-
practice opening hours and appointment availability
-
impact on patient registrations
-
staff rotas and availability
Practices should also work with ICBs to understand the impact on reporting and financial processes.
At least 4 weeks before the final data production (FDP) date, practices should meet with all key people involved. This meeting is to decide on processes to be followed.
During the cutover period the new supplier will import data into the new system.
Practices can continue to enter data into the current system. But you should be aware that it will not be migrated over. So it’s essential to keep a record for manual re-entry into the new system post go live.
Support for the old (legacy) system will continue for 90 days after go live. The practice will have access during this period.
Consideration should also be given to how the cutover period can be managed. You may wish to setup a teams chat and channel to share updates. Regular checkpoint calls will keep everyone informed of progress.
It is also important to agree with the supplier what support they will provide during and after the cutover.
Who is involved
The people, teams or organisations who might be required in this stage of the migration are:
- practice manager
- practice staff
- integrated care board (ICB)
- IT delivery partner
- current clinical system supplier
- new clinical system supplier
- third party system suppliers
- pathology labs providers
Preparation tasks
- notify third parties and linked services
- backup third party systems
- manage third party suppliers
- export templates
- handle new registrations
- clear outstanding communication tasks
- check system logoff requirements
- manage dispensary stock (dispensing units)
- check smart cards and card readers
Notify third parties and linked services
Inform all third parties (learn more about kick off and pre migration tasks). They must switch off links and communications 1 to 2 days before the final data production day.
Backup third party system
The current supplier might not back up some local or third party systems or databases. You will need to back these up.
Manage third party suppliers
Make sure you have a plan for third party suppliers. Examples include document scanning and management like DocMan or Apollo Scan.
See pre migration tasks for more information.
Export templates
Export letter and clinical templates from the current system. Import them into the new system at go live. Trainers can assist with this task.
Handle new registrations
During cutover, new patients will not be able to register online. The practice can still allow in person registrations. The data will need to be held by the practice to be put onto the new system after go live. Patients must be re-registered with full General Medical Services (GMS) after go live.
Record activities for new patients to enable entry after go live. Examples of these activities include:
- consultations
- prescription requests
Clear outstanding communication tasks
Clear:
- inboxes
- outstanding workflows
- open communication tasks, like pathology and registration
All tasks must be done by the final data production day.
Check system log off requirements
Confirm whether users need to log off the system before final data extraction. If needed, inform your team and adjust schedules to ensure a timely log off for extraction.
Manage dispensary stock (dispensing units)
Dispensing units need to reduce stock leading up to cutover. All stock will need to be re-entered into the new system after go live.
Check smart cards and card readers
Check that smart cards and card readers are up to date and working correctly.
Tasks for managing patient records during cutover
- managing appointments
- entering consultations
- recording home visits
- logging telephone calls
- prescriptions handling
- managing patient registrations
- handling pathology results
- processing referrals
- scanning documents
- redirecting screening services
- managing 111 messages and clinical correspondence
- maintaining out of hours reports
- pausing summarisation and routine data entry