Part of Migration and implementation
Preparing for migration
This chapter describes how to start preparing for a GP clinical system migration.
Preparing for migration
When the choice and selection processes are complete, migration and implementation can start.
Who is involved
The people, teams or organisations who might be required in this stage of the migration are:
- integrated care board (ICB)
- IT delivery partner (this could be a third party supplier or a team within the ICB)
- practice manager
- new system supplier
Initial preparation
- request a data extract from the current GP clinical system supplier
- arrange kick off meeting and technical assessment
Request a data extract from the current GP clinical system supplier
As part of the contractual migration process that suppliers are obliged to follow, the current GP clinical system supplier will provide a data extract from your practice to the new supplier. This will be on the initial data production date. Currently suppliers are allowed up to 15 working days to provide this extract, but actual delivery times may be less.
The ICB sends a formal data extract request to the current supplier using the data extract request template. The extract will be provided by the existing supplier to the new supplier via an internet based safe file transfer protocol.
Recommendation
Send the request to the current supplier as early as possible. Suppliers have different lead times or notice periods. Any delays may impact the migration timeline.
Arrange kick off meeting and technical assessment
Plan a date for the kick off meeting. Include all people who will work on the migration process (see the list in the kick off section).
After the kick off meeting, decide when to set up the technical assessment. See the technical assessment section for further information.
Some IT delivery partners and suppliers conduct the technical assessment remotely so may not need to be on site.